Graded separation bridge No. 16 and bridge over Route No. 4


Graded separation bridge No. 16 and bridge over Route No. 4

Execution of two bridges (except for the foundations work carried out by another contractor before Shura entered the project), one about 80m long over the Haifa-Tel Aviv railway line and the other (about 120m) over Route 4 in the Zichron Ya'akov - Or Akiva section. Construction work for the new bridges included earthwork, on-site concrete casting, main prefabricated beams, sealing, supports, expansion joints and safety railings.

 

 

Client: CPA Yitzhak Karmin, trustee of Khaldi Brothers

                  Company Earthworks Ltd.

 

Supervision: Feuerstein-Gazit Enginers Ltd.

 

Starting Date: May 2009

 

Delivery Date: April 2010

 

Scope of Implementation: Approximately 12 million NIS

 

Location: Route 4, at the entrance to Ma'agan Michael

 

 