Renovation work and improving safety at the Fuel Dock in Haifa Port

Concrete restoration of the pier platform and of the front beam facing the sea using on-site gunned and cast concrete, treatment of expansion joints and bollards, replacing fire blocking shield at the bottom of the dock, performing concrete condensation of existing cylindrical shields...

Bridge over Nahal Ada

The bridge is located on Route 6531 over the Nahal Ada creek, at the entrance to Jisr al-Zarqa. The bridge replaced an old bridge built in the 50s and in poor physical and functional condition. In order not to disrupt the traffic on the road, a temporary bypass ...

Graded separation bridge No. 16 and bridge over Route No. 4

Execution of two bridges (except for the foundations work carried out by another contractor before Shura entered the project), one about 80m long over the Haifa-Tel Aviv railway line and the other (about 120m) over Route 4 in the Zichron Ya'akov ...

Pedestrian Bridge and Elevators at the Atlit Railway Station

The work included constructing new pillars for the pedestrian bridge at the railway station (by drilling piles for the foundations), producing a perfectly constructed bridge in a metal workshop and installing it on site ...

Bridge over Sha'ar Ephraim – Trans-Israel Highway

Bridge No. 21 over Route 6, the Trans-Israel Highway, connecting Taybeh to Kalansua.

The bridge – 120m long and 60m wide – is mounted on foundation piles and massive pole heads. The end and mid-pillars are made of bare concrete ...

Haruv Bridge over Route 705, Nesher, Haifa

The bridge was built with a slight arch and slopes both length and widthwise. It consists of two edge pillars and a cast pavement on prefabricated channel beams made of reinforced and prestressed concrete. The pavement on the bridge is 7m wide with two sidewalks.

Kitchen and Dining Room at Fliman Hospital

The work included quarrying, earthwork for the basement floor and building the basement floor of bare concrete, construction of the kitchen floor in which all systems are made of stainless steel, installation of air conditioning systems ...

University of Haifa, Terrace Building 2, Law Faculty – demolition and construction

The building was already connected to an existing structure. Therefore the new structure had to be compatible and also connected to the existing structure. The uniqueness of this project was that the foundations ...

Boston House

Boston House, in Hof Shemen, Haifa is a three-story, 2,600 m2 building housing industrial companies and offices. It is divided into a ground floor (Entrance Floor) and two regular floors. The core has two elevators, two stairwells ...

Construction and Envelope - adding an extra floor to an existing building – the G2 Gym

The building (approximately 5,000 m2) was constructed on an existing floor of a shopping mall. Connections were made ​​to the existing construction, as well as columns, beams, walls, roofs, core floor protected spaces and outdoor stairs for two floors.

Upgrading the Moriah Geriatric Ward and the Main Lobby of the Sephardi Nursing Home in Haifa

Demolition and dismantling within an existing structure – block walls, plaster and flooring. Structural construction changes and constructing a new area. New electrical, plumbing and A/C systems were installed alongside finishing ...

Bridge over Nahal Keziv and regulating the Elkosh Junction

The 108m long, 15m high bridgewas built using prefabricated beams on which prefabricated membranes were cast in a special area created for this purpose. The bridge has three middle pillars and supporting walls on both access areas covered with rough stone ...

Kibbutz Yifat Culture Center

The Culture Center at Kibbutz Yifat belongs to the Jezreel Valley Regional Council and serves all local residents. Work on the site included the demolition and removal of seats in the hall, casting a concrete floor and a ramp leading to the stage ...

Operating Rooms – Bnei Zion Hospital

Rebuilding two existing floors in the hospital. The building operates 24 hours a day, making the work very difficult. The work involved demolishing interior partitions and existing concrete walls and constructing new partitions ...

Elyakim Interchange Bridge

Concrete rafts for all pillars (including the end and middle ones) form the foundation of the bridge. The end pillars are made of bare concrete walls and the middle pillars are placed on elliptical sections. The structure of the top ...

Building Hillel Yaffe Hospital Laboratories

A modern building of laboratories including all the necessary medical gas systems and a high quality finish. A technical roof was installed indoors. This houses the plumbing system making maintenance very easy ...

The Railcar Garage at Hof Shemen

Upgrading and extending a railcar garage at Hof Shemen, Haifa (120m long) ...

Bridge over Nahal Besor

The bridge is located near the Gaza Strip and used chiefly as a passageway for armored vehicles and tanks. The work included prefabricated concrete works, on-site casting and electrical and communication system work for lighting and traffic lights.

Railway Bridge over Nahal Sorek

The work included the complete demolition and removal of the existing railway bridge, earthmoving and drilling piles for the new foundations, pumping groundwater, on-site concrete casting works, on-site casting of prefabricated elements (membranes) ...

Civil Engineering Works for Two Gas Turbine Units at Ramat Hovav

In this project – the first under the government's emergency electricity plan implemented in early 2008 – the company performed all the civil engineering work in constructing two new gas turbines (6 and 7) at the Ramat Hovav power station...

Renovating bridges over Nahal Zin, demolition and re-building of two bridges over Nahal Hayun and restoring the road on Route 90

The work involved demolishing two bridges over the River Hayun and building two new modern bridges to replace the old ones, as well as massive renovation of different elements of the Nahal Zin Bridge (mainly main beams and pavement) on the Arava Road ...

Addition of a Catheterization and Intensive Care Ward - Poriah Hospital

Demolition of an existing ward and building ICU rooms. The work included installing finishing details, radiation-proof lead-glass (including a radiation-protected room) and special systems such as air conditioning and medical gas supply lines ...

Bridge over Nahal Kti'a, Road 705, Nesher, Haifa

The bridge is divided into two distinct sections with 3m between them. One section bears the ascending road and the other the descending road. Each section is comprised of two lanes and a parking shoulder ...

Building 23 (Microsoft) Matam

This is a four-story, 4,300 m2 building. The ground floor includes an industrial area, the dining room and a kitchen. The core consists of one elevator, two stairways and shafts for the various systems reaching the entire height of the building ...

Kitchen and Dining Room at Poriah Hospital

The project consisted of building a central kitchen to serve the entire hospital and a dining room for the staff.The work included a double floor, stainless steel ducts, advanced sealing systems and granite porcelain flooring with epoxy grout ...

Construction of the Biology Faculty at the Technion in Haifa

The building contains research laboratories, classrooms and offices. Construction work included earthwork and concrete cast on site, building construction, finishing works such as sealing, insulation, carpentry, sanitation, electrical systems ...

Renovation of Beer-Sheva and Hevron Bridges on Beer-Sheva - Dimona's railway line

This project includes the construction of two bridges: Hevron and Beer-Sheva Bridges.

The bridges will be built parallel to the existing bridges. Since the railway line is active, at first stage a new foundation will be completed. Then the running of the train system will be halted for a week and In that period of time, the new bridges will be placed upon the new foundation, followed by the placing of the tracks.

Wheels Garage at Israel Railways

The Ephraim Workshop wheels garage project includes demolition of an 800m2 storage building and construction of a new concrete structure with a steel roof. In addition, the project involves upgrading the existing 1,500m2 garage including the supply and installation of cranes and special equipment...

Bridge over Nahal Zipori on Deshanim Route 772

In its final form, the bridge is designed as two adjacent and parallel bridges, each carrying two lanes of traffic and shoulders. The bridges are detached from each other but share edge piles (at both ends.) Within the scope of the current project...

Replacement of Lehavot Habashan bridge and Goma bridge

This project is the replacement of two old bridges from the 50's, narrow and one-way traffic, which are located above the eastern canal of the Jordan River, one on road 977 near Kibutz Lehavot Habashan, and the second on road 977 near Goma junction.

The project includes:

Foundations that are made of concrete piles drilled and cast in place

Reinforced concrete abutments and U shaped pre-stressed beams with cast in place concrete slab, retaining walls.

Accessibility